Time: 2021.05.19 14:05 Click: 758
1#Blast furnace hot blast stove intelligent combustion system officially put into use.
On September 19, Guangxi Iron and Steel Group Co., Ltd. Fangchenggang Iron and Steel Base 1# blast furnace hot blast stove intelligent combustion system was put into production.
The system began to be commissioned on August 18th, and after one and a half months of intense commissioning work, it was successfully completed on September 31th, 2020. Up to now, the system has been operating stably.
Today, we are facing an era of rapid economic development, and economic development is inseparable from the drive and support of science and technology. As the crystallization of modern science and technology and modern industry, automation technology is an important symbol of industrial modernization and the core force of modern advanced science.